Use when tracking and controlling a PMBOK project. pm:monitoring — measure project performance with EVM, manage integrated change control, control scope/schedule/cost/quality, implement corrective actions.
How this skill is triggered — by the user, by Claude, or both
Slash command
/thyrox:pm-monitoringThis skill is limited to the following tools:
The summary Claude sees in its skill listing — used to decide when to auto-load this skill
> *"Monitoring without controlling is just watching a car drive off a cliff. The value of performance measurement is not the measurement itself — it's the corrective action it enables before the project goes too far off course."*
"Monitoring without controlling is just watching a car drive off a cliff. The value of performance measurement is not the measurement itself — it's the corrective action it enables before the project goes too far off course."
Ejecuta el Grupo de Proceso Monitoring & Controlling de PMBOK. Mide el rendimiento del proyecto con EVM, gestiona el Control de Cambios Integrado, controla el scope/schedule/cost/quality, e implementa acciones correctivas y preventivas.
THYROX Stage: Stage 11 TRACK/EVALUATE (corre en paralelo con Stage 10 IMPLEMENT).
Outputs clave: Work Performance Reports · Change Requests · Corrective/Preventive Actions.
flowchart TD
E[Executing\nWork in progress] --> COL[Recopilar\ndatos de desempeño]
COL --> EVM[Calcular EVM\nSV/CV/SPI/CPI]
EVM --> VAR{Varianza\nacceptable?}
VAR -->|Sí| REP[Informe de\ndesempeño]
VAR -->|No| CA[Acción correctiva\no preventiva]
CA --> ICC[Integrated\nChange Control]
ICC --> REP
REP --> E
style EVM fill:#4a9eff,color:#fff
Requiere: {wp}/pm-planning.md con:
| Knowledge Area | Proceso de Control |
|---|---|
| Integration Management | Monitor and Control Project Work · Perform Integrated Change Control |
| Scope Management | Validate Scope · Control Scope |
| Schedule Management | Control Schedule |
| Cost Management | Control Costs |
| Quality Management | Control Quality |
| Resource Management | Control Resources |
| Communications Management | Monitor Communications |
| Risk Management | Monitor Risks |
| Procurement Management | Control Procurements (si aplica) |
| Stakeholder Management | Monitor Stakeholder Engagement |
EVM integra scope, schedule y cost en una sola visión de desempeño. Referencia detallada con todas las fórmulas: references/evm-and-change-control.md.
Variables clave: PV · EV · AC · BAC
Métricas de varianza: SV = EV−PV · CV = EV−AC · SPI = EV/PV · CPI = EV/AC
SPI/CPI = 1.0 perfecto · > 1.0 ahead · < 1.0 behind. Umbral de alerta: < 0.85.
Métricas de proyección: EAC = BAC/CPI · ETC = EAC−AC · VAC = BAC−EAC · TCPI = (BAC−EV)/(BAC−AC)
TCPI > 1.10 → BAC prácticamente inalcanzable; ajustar EAC con el sponsor.
ADVERTENCIA: EVM identifica QUÉ está pasando, no POR QUÉ. El análisis de causas requiere investigación adicional.
Además de la perspectiva EVM, controlar el cronograma en términos de actividades y hitos:
| Actividad | Descripción |
|---|---|
| Actualizar el cronograma | Reflejar el progreso real en el cronograma de actividades |
| Analizar el Critical Path | Identificar si hay actividades críticas con float negativo |
| Análisis de compresión | Si hay retraso: Fast Tracking (actividades en paralelo) o Crashing (agregar recursos) |
| Forecast to completion | Proyectar fecha de completion basada en progreso actual |
Opciones de compresión del cronograma:
| Técnica | Descripción | Riesgo |
|---|---|---|
| Fast Tracking | Poner actividades en paralelo que estaban en serie | Aumenta el riesgo de retrabajo por dependencias |
| Crashing | Agregar recursos al Critical Path para acelerar | Aumenta el costo; rendimientos decrecientes |
Todo cambio al scope, schedule o cost baseline pasa por el CCB (Change Control Board). Proceso completo y template CR en references/evm-and-change-control.md.
Flujo resumido: Identificar cambio → Crear Change Request → Evaluar impacto → Presentar al CCB → Decisión (Approve/Reject/Defer) → Implementar si aprobado → Comunicar → Actualizar baselines.
Quality Control inspecciona los deliverables para detectar defectos:
| Técnica | Cuándo usar | Output |
|---|---|---|
| Inspección | Todo deliverable antes de entregarlo | Defect log |
| Testing | Deliverables de software o sistemas | Test results |
| Statistical sampling | Cuando no es viable revisar el 100% (ej: manufactura) | Sample results + inferencia |
| Checklist verification | Verificar que todos los criterios de aceptación están cumplidos | Completed checklist |
QC detecta defectos; QA previene defectos. Ambos son necesarios.
En Monitoring & Controlling, el Risk Register se revisa y actualiza periódicamente:
| Actividad | Frecuencia |
|---|---|
| Revisar estado de riesgos activos | Cada periodo de reporte |
| Verificar si triggers de riesgo se cumplieron | Continuo durante ejecución |
| Identificar nuevos riesgos emergentes | Continuo |
| Actualizar probabilidad/impacto de riesgos existentes | Cuando cambia el contexto |
| Ejecutar planes de respuesta para riesgos materializados | Cuando el riesgo ocurre |
| Varianza | Acción requerida |
|---|---|
| SPI o CPI entre 0.90 y 1.10 | Monitoreo normal — no se requiere acción correctiva urgente |
| SPI o CPI entre 0.85 y 0.90 | Análisis de causa + plan de corrección — reportar al sponsor |
| SPI o CPI < 0.85 | Acción correctiva inmediata + Change Request si impacta baseline + escalación al sponsor |
| TCPI > 1.10 | Revisar EAC con el sponsor — el BAC original puede requerir ajuste formal |
{wp}/pm-monitoring.md
usar template: performance-report-template.md
Monitoring & Controlling es continuo — no tiene completitud propia sino condiciones de cierre:
| Condición | Acción |
|---|---|
| Todos los deliverables verificados y aceptados por QC | Activar pm:closing |
| Varianza crítica (SPI/CPI < 0.85) | Change Request + acción correctiva + continuar Monitoring |
| Todos los contratos cerrados (si aplica) | Iniciar pm:closing en paralelo |
Al INICIAR este step:
methodology_step: pm:monitoring
flow: pm
pm_process_group: monitoring_controlling
Activo en paralelo con Executing:
methodology_step: pm:executing+monitoring
flow: pm
pm_process_group: executing+monitoring_controlling
Al COMPLETAR (todos los deliverables verificados → cierre):
methodology_step: pm:monitoring # completado → activar pm:closing
flow: pm
pm_process_group: monitoring_controlling
pm:closingGuides creation, editing, and verification of skills for AI coding agents using test-driven development with subagent scenarios. Use when authoring or debugging skills.