From contractor-subs
Build a monthly progress payment application against a schedule of values — percent complete, previous billings, stored materials, retainage math, and the lien waiver reminder. Use when the user says "pay app", "progress billing", "monthly invoice to the GC", or "/sub-pay-app".
How this skill is triggered — by the user, by Claude, or both
Slash command
/contractor-subs:sub-pay-appThe summary Claude sees in its skill listing — used to decide when to auto-load this skill
The monthly billing ritual. Build a payment application against your schedule of values: what's complete, what was billed before, what's due now, with retainage math that actually adds up. Follows the G702/G703 continuation-sheet conventions GCs expect, without reproducing AIA forms (if the GC mandates actual AIA forms, this output gives you every number to transcribe).
The monthly billing ritual. Build a payment application against your schedule of values: what's complete, what was billed before, what's due now, with retainage math that actually adds up. Follows the G702/G703 continuation-sheet conventions GCs expect, without reproducing AIA forms (if the GC mandates actual AIA forms, this output gives you every number to transcribe).
SCHEDULE OF VALUES — APPLICATION #4, PERIOD ENDING [date]
─────────────────────────────────────────────────────────────────────────────
Item Description Sched. Prev. This Stored Total % Balance
Value Billed Period Mat'l to Date to Finish
─────────────────────────────────────────────────────────────────────────────
1 Mobilization $8,000 $8,000 — — $8,000 100 —
2 Rough-in L1 $64,000 $48,000 $16,000 — $64,000 100 —
3 Rough-in L2 $64,000 $12,800 $25,600 — $38,400 60 $25,600
4 Fixtures $41,000 — — $12,300 $12,300 30 $28,700
CO1 Added BMS scope $8,400 — $4,200 — $4,200 50 $4,200
─────────────────────────────────────────────────────────────────────────────
TOTALS $185,400 $68,800 $45,800 $12,300 $126,900 $58,500
1. Original subcontract sum $177,000
2. Net change by approved COs $8,400
3. Subcontract sum to date (1+2) $185,400
4. Total completed & stored to date $126,900
5. Retainage ([X]% of line 4) $(12,690)
6. Total earned less retainage (4−5) $114,210
7. Less previous applications $(61,920)
8. CURRENT PAYMENT DUE $52,290
9. Balance to finish, incl. retainage $71,190
Verify every cross-foot before output: continuation sheet totals must equal line 4; line 7 must equal the prior app's line 6. If the numbers don't tie, stop and reconcile — a pay app that doesn't tie gets rejected and costs a month.
{company-slug}_payapp_{NN}_{project-slug}_{period}.xlsxnpx claudepluginhub sunrise-systems/contractor-toolkit --plugin contractor-subsProvides UI/UX resources: 50+ styles, color palettes, font pairings, guidelines, charts for web/mobile across React, Next.js, Vue, Svelte, Tailwind, React Native, Flutter. Aids planning, building, reviewing interfaces.